Fact Sheet Hybrid Energy Center-Clinch River
138kV Double Circuit Transmission
Line
Project Scope
This application for an approximate 8.8-mile, double circuit
138kV transmission line is being submitted by Dominion Virginia Power as a
means to connect a proposed coal-fired power station in Virginia City, Va.,
to the existing electrical grid system. Dominion
Virginia Power has already submitted an application for the Virginia
City Hybrid Energy Center, which will generate 585
MW of electrical power when completed. Existing electrical transmission capabilities
in Wise County and Russell County are inadequate to accept power from the planned
station.
Location
This proposed line originates in Wise County, Virginia
at the Company’s proposed
coal plant and terminates at a proposed substation near AEP's Clinch
River Steam Plant in Russell County. >> View
a map.
Structure Types
Two types of structures are being considered, and Dominion
proposes to utilize either one of these, or a combination of the two. >> View
the structures.
Regulatory Approvals Required
The proposed construction of a new double-circuit, 138kV
line requires approval from the Virginia State Corporation Commission (SCC),
and Dominion filed an application for this project on Dec. 3, 2007. The SCC
is responsible for determining the need, route, and environmental impact of
transmission lines in Virginia. Anyone may
comment to the SCC concerning our plans. VDOT
permits will be required for road crossings. Any wetlands impacts will
require a JPA to be submitted, and may or may not qualify for NW12.
Planned Project Schedule
A line is required for backfeed by November 1, 2010. Initial
synchronizing with the coal plant is planned for August 15, 2011. Below is
a detailed project schedule:
July 2007
SCC application filed for Virginia
City Hybrid Energy Center
Dec. 2007
SCC
application filed
for proposed double-circuit, 138kV Transmission Line
April 2008
Begin construction of theVirginia
City Hybrid Energy Center
May 2008
Begin right-of-way acquisition for the transmission
after SCC approval
September
2009
Begin construction of the Transmission Line
September
2010
Transmission line to be placed in service to Virginia
City Hybrid Energy Center