The Virginia State Corporation Commission (SCC) approves all
electric transmission facilities of 138,000 volts (138 kV) and above, which
includes this project. Dominion submitted an application to the SCC for approval
of this project on May 4, 2007. The SCC has held all public hearings regarding
this project and the Hearing Examiner issued a report to the SCC Commissioners
on May 1, 2008. The Commissioners reviewed all of the evidence and the Hearing
Examiners recommendation and issued an Order
on October 31, 2008 granting approval of the project.
Select "SEARCH CASES" on the navigation across
the top of the page. Enter the Case Number in the "Enter Case Number"
field and click on "Search."
| Volume I |
|
| Volume II |
|
| Volume III |
|
| Supplemental Direct Testimony - 07-13-2007 |
- SCC Cover Letter
- Stephen G. Thornhill - Revised aerial maps were included with this supplemental testimony.
- Elizabeth Harper
- Testimony
- Summary of Changes
- Maps - (revised 10/02/07) This file includes an index sheet and 11 maps. (This file includes an index sheet and 11 maps. Individual maps can be viewed by clicking on the boxes on the index sheet or by using the bookmarks.)
|
| Order of Notice and Hearing |
|
| Second Supplemental Direct Testimony - 10-03-2007 |
- Stephen G. Thornhill - Revised aerial maps were included with this supplemental testimony.
- Elizabeth Harper
- Testimony
- Summary of Changes
- Maps - (revised 10/02/07) This file includes an index sheet and 11 maps. (This file includes an index sheet and 11 maps. Individual maps can be viewed by clicking on the boxes on the index sheet or by using the bookmarks.)
|
| Hearing Examiner's Report |
|
|